Major Projects
| The Mall at Robinson |
 |
Retail Complex
Robinson Township, PA
$8,525,000
Installation of erosion and sedimentation controls, clearing and grubbing, and excavation of 2,600,000 cubic yards of mass earth for the construction of a regional shopping mall. |
The Waterfront Development |
 |
Retail/Entertainment Complex
Homestead, PA
$5,100,000
Site development for a 100+ acre retail/residential project.
Work items included erosion controls, complete excavation for roadways, storm and sanitary sewer systems, installation of electric and telephone conduit banks, and complete asphalt paving.
|
The Pointe at North Fayette |
 |
Retail Complex
North Fayette Township, PA
$14,700,000
Site development and infrastructure for retail pads including Home Depot, Petsmart, Wal-Mart, Sam’s Club, Circuit City, Best Buy, Target, and a strip mall.
Excavation of 6,450,000 cubic yards, erosion and sedimentation controls, clearing and grubbing, and installation of underground utilities. |
CONSOL ENERGY
Enlow Fork Mine, Phases I and II
Overland Conveyor Sitework |
 |
Overland Coal Conveyor
Corridor Development
East Finley, PA
$15,000,000
Installation of erosion and sedimentation controls, clearing and grubbing, common and hard rock excavation, conveyor culverts, waterline and access road construction for the development of a six and one-half mile overland coal conveyor corridor.
|
Century III |
 |
Slag Handling
West Mifflin, PA
$9,000,000
Excavation, transportation and stockpiling of 3.5 million yards of steel slag to prepare commercial development pads for Home Depot, Giant Eagle and Kohl’s.
Excavation was fast tracked and completed in nine months.
|
Anker Energy |
 |
Sycamore Creek Face Up
Clarksburg, WV
$1,100,000
Excavation of 490,000 cubic yards of earth and rock for a coal mine entrance.
Clearing and grubbing, ditch work, mass excavation, gates and fences, and seeding and mulching. |
|